Area 3 Construction

Sheridan Boulevard (right)
Sheridan Boulevard bridge work is complete and punch list work will begin mid January.










Perry Street - Knox Court (left)
In mid December West Rail crews opened Perry Street in its final configuration. Punch list work on Perry Street will begin mid January.  Perry Street bike path reconstruction is ongoing.  Knox Court construction continues as crews will install abutment hand rails, the fire hydrant, and overhead catenary system (OCS) foundations.  Work on the Hazel Court bike path continues.


Federal Boulevard (right) - South Platte Bridge
Crews have completed work on the Federal Channel and will begin punch list work in mid January. Work on the Decatur/Federal Station (pictured at right) continues.  Through January, crews will continue work on the walls, install the  overhead catenary system (OCS) foundations, begin track work at the station, and install the light pole foundations.


Zuni Street (left) 

Early to mid January crews will complete underground storm drain work, as well as complete track work in the area by placing the top ballast.




 



Auraria Campus
West Rail crews have completed work on the Auraria Station and are installing the final signage in the area. Additionally, in late December crews finished paving the Auraria Campus parking areas. To complete storm and drain work in the area, crews closed 5th Street at Lower Colfax and will remain closed until mid January.  Thereafter, crews will open 5th Street and close Lower Colfax at 5th Street through mid January.